September 9, 2014

Progress Made on Balconies

There has been some progress made in tearing down and replacing balconies at Greentree.  The photo below was shot on September 5th of the two balconies (of 42 to be done) that had been torn down on a month earlier, on August 4th.



Photos below were shot on September 8th.  The first two are of the back of Building B and show that four more balconies have been removed.  The last photo shows that some work has begun for balconies on the front side of that building.




Photos below were shot on September 9th at the end of the day, showing that the balconies on the back of Building B are now almost all down; there were eight there to be removed. The third photo shows the progress made so far on the two torn down on August 4th. The last photo shows that removal of one of the balconies on the front of the building has begun.







At this rate, it shouldn't take more than a year or two for the job to be completed.